The newest copper cabling standard added a pass/fail test for high-power PoE. Most installed links were never tested for it, and no rule forces your next project to be, unless someone writes it into the specification.
ANSI/TIA-568.2-E sets hard limits on DC resistance unbalance, or DCRU: 3% within-pair and 7% pair-to-pair, with a 0.20 ohm cap in both cases. Why it matters: under high-power PoE, those four pairs are carrying DC current as well as data. When the resistance between pairs or within a pair is uneven, current loads unevenly too. The result is extra heat in the cable and the powered equipment, distorted Ethernet signals, and packet errors that show up as flaky cameras, access readers and access points long after the installer has left the site.
Here is the part facility owners and IT managers should know: a standard link certification can pass while skipping DCRU entirely. Field testing for it is not yet mandatory industry-wide. It only gets run when the project specification, the manufacturer's warranty program, or the customer asks for it. A link can be "certified" and still carry a resistance imbalance that surfaces as heat and dropped packets on a 90W camera or access point two years in.
What this means in practice:
1. If your facility runs or plans high-power PoE (90W cameras, Wi-Fi 6E/7 access points, displays, building controllers), make DCRU testing part of the cabling specification before the contract is signed.
2. Ask which test limits your installer certifies against. Modern field testers report DCRU as a pass/fail result; a report that omits it tells you the test was not performed.
3. Remember that poor terminations are a leading cause of DCRU failures, so the test is also a window into workmanship quality.
At OVC-Cabling we certify copper runs to current standards and test for the parameters that high-power PoE actually stresses, not just the ones a legacy checklist mentions. If you are budgeting cameras, access points or building devices that draw serious power, ask us what your specification should say before the cable goes in the ceiling.